Standardize the in plant commissioning requirements according to overseas commissioning standards
Affected by the global epidemic, the domestic epidemic has shown a trend of continuous fluctuation and decline, and comprehensive prevention and control have effectively reduced new infections. In order to prevent the rebound of epidemic situation in some areas, all units implement closed-loop management, lengthen personnel isolation time and other prevention and control measures.
According to the commissioning experience of equipment sent overseas in the past, the double head sub motor aluminum puller sent to Malaysia a2106008 this year was made into a standardized commissioning manual by yangminglin, the overseas regional service manager of our company, after commissioning and checking the equipment in strict accordance with the in plant commissioning requirements, and remotely guided the customer to operate the site to assist in commissioning according to the commissioning manual. On May 5, it took only one day to complete the empty machine no-load commissioning, which greatly shortened the commissioning time. Gear oil was added on May 11, and the finished product line and wire specifications were successfully produced on May 14 Ф 2.46mm, and the production speed is 1500m/min, which all meet the contract production requirements and have been highly praised by customers.
Preparation of commissioning manual
In order to improve the efficiency of off-site commissioning and standardize on-site commissioning, we should learn from overseas commissioning experience and promote remote guidance commissioning. On May 18, the Service Center convened all service personnel in the company to hold a meeting in conference room 4 to discuss the necessity of strengthening in plant commissioning. Through communication, all service personnel agreed to strengthen the important impact of in plant commissioning on off-site commissioning and improve the commissioning effectiveness. It was determined at the meeting that: add signboards at both ends of each connecting line to mark the connection position, and check each word code in the electric cabinet one by one to ensure that the drawing is consistent with the on-site physical object, so as to ensure the accuracy of line connection, ensure the normal no-load commissioning after connecting according to the wiring diagram of the drawing, and keep the in plant commissioning records for the reference of off-site commissioning.
Pictures of in plant commissioning records
Service Center correspondent: wangyanjia |